The proposed development will include 48 high-quality residential units and 1 commercial unit, designed to enhance the local area. Construction is scheduled to begin on 20th October 2025 and will run for approximately 20 months.
- Piling: 20/10/2025 to 30/11/2025
- Substructure: 30/11/2025 to 01/05/2026
- Superstructure: 01/05/2026 to 11/07/2027
This website will provide regular updates, key documents, and opportunities to give feedback on how we manage construction activity. Our aim is to ensure that the development proceeds smoothly while maintaining the safety and quality of life for everyone in the surrounding area
Public Consultation on Construction Management Plan (CMP)
Site Address:
34–40 White Church Lane & 29–31 Commercial Road, Whitechapel, London
Dear Neighbor,
We are writing to inform you about our upcoming development at the above address and to invite you to provide your comments on the Construction Management Plan (CMP), which outlines how we will manage construction works to minimize disruption to the local community.
About the Project
The proposed development comprises:
– 48 residential units
– 1 commercial unit
Construction is scheduled to commence on 20th October 2025, with an estimated programme duration of 20 months. Please see below the indicative dates for the key construction phases:
- Piling: 30/06/2025 to 04/08/2025
- Substructure: 04/08/2025 to 01/09/2025
- Superstructure: 15/12/2025 to 11/10/2026
About the CMP
The CMP sets out how construction activities will be managed, including:
– Site working hours
– Construction traffic routing
– Noise and dust mitigation
– Site access and logistics
– Waste management
This consultation is specifically about the Construction Management Plan, not the development itself, and is required to ensure local residents and stakeholders have an opportunity to review and comment on the construction approach.
How to View the CMP
The full CMP document can be viewed or downloaded at the following website:
http://www.wcldevelopment.co.uk
Have Your Say
We welcome your feedback and encourage you to submit any questions, comments, or concerns to wcldevelopment@cmtconstruction.co.uk by 4th July 2025.
We will consider all comments received prior to finalizing the CMP for submission to the London Borough of Tower Hamlets
Thank you for your attention and cooperation. We are committed to being a considerate neighbor and delivering this project with as little disruption as possible.
Yours sincerely,
David Gentry
Project Lead
CMT Design & Construction Ltd
wcldevelopment@cmtconstruction.co.uk